The program of capital repairs of apartment buildings is entering the final stage

25 July 2022, Monday

The program of major repairs of apartment buildings in Tatarstan has been completed by 79%. The final stage included work in 67 houses. In 87 residential facilities, the work has been completed completely. Such data were presented by the Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin at a republican meeting in the Government House of the Republic of Tatarstan with the participation of Prime Minister Alexei Pesoshin.

The overhaul of educational facilities has been completed by 66%. Of the 22 kindergartens, 20 remain in operation, the completion of work is 67%. The Minister recalled the need to complete the overhaul of all educational facilities by August 20.

More than half of the total number of primary care facilities implemented under federal and republican programs have been commissioned under the Healthcare line. Construction and installation work on them was completed by 66%. According to the republican program of capital repairs of hospitals, 24 objects were repaired – 77% of the total volume of construction and installation works.

The performance of works under the “Culture” program was 68%. In the field of ecology and protection of natural resources, 2 program activities are being implemented. In general, their implementation is estimated at 46%. The contractors still have 28 objects in operation. Three objects are completed.

The program of repairing youth centers has been completed by 68%. The program for the repair of health camps, which also includes 6 facilities this year, has been completed by 61%.

According to the program “Providing the population with drinking water", construction and installation works were completed by 47%. According to the program “Reconstruction and overhaul of gas consumption networks with replacement of boilers in boiler rooms of budgetary institutions”, 22 objects out of 40 are in the work of contractors. This week, work has been completed in Aznakaevsky, Aktanyshsky, Yelabuga, Leninogorsk, Mamadyshsky, Menzelinsky, Muslyumovsky, Nizhnekamsk and Sarmanovsky districts. The completion of the work was 74%.

Works on 18 objects of the program “Reconstruction and construction of gas distribution networks, indoor gas consumption networks, installation of block-modular boilers and outdoor boilers in cities and districts” were completed by 34%.

More than half completed the construction of a water supply system with a water intake node for the city of Nurlat within the framework of the federal project “Clean Water”.