The construction of an extension to gymnasium No. 19 in the Volga region of Kazan is 51% complete. The construction of the building was caused by a significant excess of the designed capacity. Currently, 1,813 children are studying in the school with 800 places.
To date, work has been completed on brickwork on the first and second floors, monolithic construction, installation of parapets on the roof, and plastering of the basement.
Ventilation installation is 86% complete, the façade is 60% insulated. Electrical work on the basement is 95% completed, and on the first floor - 60%.