A kindergarten for 220 places in the Novo-Savinovsky district of Kazan is 48% ready

6 October 2023, Friday

The construction of a kindergarten in the Novo-Savinovsky district of Kazan is 48% complete. Brickwork and floors are ready at the site, basement waterproofing and roofing are completed.

Now the builders are plastering the floors, performing finishing work and laying utility networks. In parallel, the installation of windows (85%) and the construction of the facade (66%) are underway. In the adjacent area, workers are erecting shady canopies, a platform for strollers and garbage containers. Construction is being carried out according to the national project “Demography”.

The kindergarten will be attended by 220 children. It is already known that 12 groups will be opened for children, including four nurseries for children from 1.5 to 3 years old.

Let us remind you that another preschool institution with 220 places was recently built near the kindergarten under construction. It houses music and sports halls, a psychologist’s office and a large co-working center for family master classes.

SUBSCRIBE FOR NEWS
All content on this site is licensed under
Creative Commons Attribution 4.0 International